JDS Silver purchased the Silvertip Pb-Zn-Ag project from Silvercorp in late 2013 and completed a PEA outlining a 1,000 tpd operation mining 1.4M tonnes at 365 g/t silver, 0.5 g/t gold, 7.2% lead, and 8.7% zinc. JDS constructed the mine in just 10 months from December 2015, utilizing the purchased Sa Dena Hes crusher/processing plant augmented with a paste plant from Diavik.

Infrastructure included 120' bridge, 26km access road upgrades, 150-bed camp, 640 foundation piles, 3,000 m³ concrete, 2,000 m² mill building, 7.5MW LNG powerplant, 150 m³/hr water treatment plant, 12,000 m² ponds, dry stack tailings facility, in-valley leach pad, and 26,000 m³ event pond. Primary equipment (150hp jaw crusher, 1,000hp SAG mill, 900hp ball mill, flotation cells, paste plant) was purchased used, transported (190 loads), and refurbished on-site. JDS provided underground startup support including shotcreting, CRF, services, and dewatering. The project was completed safely with 256,043 hours worked and zero LTIs, on budget and on schedule.

Previous
Previous

Escobal Mine

Next
Next

Golden Meadows